Static branch assignments are used when all assignees (ex: approvers) must complete a task before allowing a Flow to continue. 


Explanation

The Branch step creates two paths. Each path has a Run Flow step that contains an Add Task step that is assigned to different users. 

Reference Articles



Project Download

The examples attached were developed to be instructional and were not developed as officially supported components. For more information or to engage our service team to develop fully supported, production-quality solutions, please contact services@decisions.com. Import the project below to a Decisions environment on version 8.5.0 or later using our Importing/Exporting article.